I-90 POST FALLS ACCESS IMPROVEMENTS STUDY |
| Documents in the I-90 Post Falls Access Improvements Study are in Flash or Adobe PDF format. You must have Adobe Acrobat Reader or Macromedia Flash 6 to access these files. |
 |
Some documents on this web site are PDF files and may be viewed using Adobe Acrobat Reader. You may download the latest version of Acrobat Reader for free by clicking on the icon on the left. |
 |
Some documents on this web site are SWF files and may be viewed using Macromedia Flash. You may download the latest version of Macromedia Flash Player by clicking on the following link. Flash Player is a FREE download.
http://macromedia.com |
|
|
Table of Contents
|
The Table of Contents link provides the reference for all documents, maps and newsletters. |
Introduction
Initial Alternatives 1 -7
Typical Sections
Aerial
Newsletters
Announcements / Press Releases
|
|
INTRODUCTION |
|
Introduction |
|
INITIAL ALTERNATIVES 1 - 7 |
|
| Alternative Combination 1 Map
Top of Page |
Alternative Combination 1
This alternative combination includes the following features:
· SH 41 Interchange Modifications
· Expansion of SH 41 to Six Lanes
· Split Diamond between Spokane Street and Idaho Street with Removal of Seltice Way Ramps
· Greensferry Road Interchange
In addition to the combined features, this alternative will have auxiliary lanes on I-90 from Idaho Street to SH 41. |
| Alternative Combination 2 Map
Top of Page |
Alternative Combination 2
This alternative combination includes the following features:
· Crossing at Greensferry Road
· Expansion of SH 41 to Six Lanes
· Seltice Way Folded Diamond Interchange
· SH 41 Interchange Modifications
In addition to the combined features, this alternative will have auxiliary lanes on I-90 from Spokane Street to SH 41. |
| Alternative Combination 3 Map
Top of Page |
Alternative Combination 3
This alternative combination includes the following features:
· Crossing at Greensferry Road
· Expansion of SH 41 to Six Lanes
· Raised Medians/Access Control on Seltice Way
Button Hook Ramp from SH 41 to Eastbound I-90 |
| Alternative Combination 4 Map
Top of Page |
Alternative Combination 4
This alternative combination includes the following features:
· Crossing at Greensferry Road
· Expansion of SH 41 to Six Lanes
· Split Diamond with Frontage Roads between Spokane Street and Seltice Way
· Raised Medians/Access Control on Seltice Way
· Button Hook Ramp from SH 41 to Eastbound I-90 |
| Alternative Combination 5 Map
Top of Page |
Alternative Combination 5
This alternative combination includes the following features:
· SH 41 Interchange Modifications
· Expansion of SH 41 to Six Lanes
· North/South Link from Seltice Way to 4th Avenue
· Greensferry Road Interchange
In addition to the combined features this, alternative will have auxiliary lanes/collector distributor roads on I-90 from Spokane Street to SH 41. |
| Alternative Combination 6 Map
Top of Page |
Alternative Combination 6
This alternative combination includes the following features:
· Overpass at Syringa Street
· Crossing at Greensferry Road
· Expansion of SH 41 to Six Lanes
· Seltice Way Folded Diamond Interchange
· SH 41 Interchange Modifications with Seltice Way Realignment
In addition to the combined features, this alternative will have auxiliary lanes on I-90 from Spokane Street to SH 41. |
| Alternative Combination 7 Map
Top of Page |
Alternative Combination 7
This alternative combination includes the following features:
· Greensferry Road Interchange
· Expansion of SH 41 to Six Lanes
· Remove Ramps at Seltice Way
· SH 41 Interchange Modifications
In addition to the combined features, this alternative will have auxiliary lanes/collector distributor roads on I-90 from Spokane Street to SH 41. |
TYPICAL SECTIONS |
|
| I-90 Six Lanes Typical |
|
| I-90 with Aux Lanes |
|
| I-90 with Collect Roads
Top of Page |
|
AERIAL |
|
| Small Aerial Map
Top of Page |
|
NEWSLETTERS |
|
|
| Top of Page |
|
ANNOUNCEMENTS / PRESS RELEASES |
|
| Open House Scoping Meeting - June 9 |
SH 41 interchange Design Concepts for the I-90 Post Falls Access Improvements project |
| Top of Page |
|